Hi,

Can anyone guide me to if it is possible to select multiple activities and then assign (a) resource(s) to them in bulk?

Thanks for any guidance.

Regs,

mike


 
Posté : 20 Août AM 09:088
(@babynus)
Posts: 14952
Membre Admin
 

No,
simply because you must specify the assigned work for the resource on each tasks...

But there are some automations, for instance that can automatically assign responsible of activity. So changing responsible on several tasks (through multiple updates mode) may fit your need.


 
Posté : 20 Août PM 20:088