Forum

[SOLVED] Cascaded s...
 
Notifications
Retirer tout

[SOLVED] Cascaded status change

2 Posts
2 Utilisateurs
0 Reactions
1,897 Vu
(@cmarti)
Posts: 65
Estimable Member
Début du sujet
 
[#7427]

Is it possible to have a cascaded status change?
I would like that a parent task which has its first child going on a "in-progress" type of status automatically impose (if not yet set) the first in-progress status of the parent.
As well the last "done" or "closed" type of status would impose the same kind of status for the parent.

I understand that it could be tricky as the type of flow could be fairly different, but I could imagine that with the order in the status values it should be possible to determine which is the first "in-progress", "done" or "closed" status.

Or maybe it is already there and I didn't catch it correctly?


 
Posté : 18/03/2021 7:50 pm
Gautier
(@gautier)
Posts: 207
Membre Admin Registered
 

Hello,

It is not yet possible in projeqtor
You can only force close or delete with a specific access.


 
Posté : 19/03/2021 4:42 pm
Share:
Retour en haut