Hello,

I would like to know if it is possible to change the setting of the automatic coding of the WBS.
The automatic format on ProjeQtOr is as follows: 1.1; 1.2; 1.2.1; etc.
I would like to know if it is possible to change this format to another one. Example: RST-P-A-1; RST-P-D-1; RST-P-D-2; etc.

Thank you in advance.


 
Posté : 20/02/2025 1:14 pm
(@marylene)
Posts: 592
Membre Admin
 

Hello

No, it is not possible. On the other hand, you have the references available which can be customized.


 
Posté : 24/02/2025 11:49 am