I have a question asked people to help fo resource cost. When I create and assign initial cost for employee A is 500.000VND / d. But when that resource assigned to the activity, only 100.000nvd / d. Thanks to everyone for helping why is there this difference?
Thanks everyone.
Details with photos attached.
Hi,
It is because internal format for dailyCost and newDailyCost is 7,2 (five digits+2 decimals)
You currency used larger numbers.
You should increase internal format or possibly use another format for currency (1KVND=1KiloVND=1000VND)