Hello,
In our current Project management, we have one user/resource assigned as a responsible for a Project. Same responsible is automatically assigned as a Project member which can have Project tasks allocated, if there is any what is not mandatory.
Is there a way in ProjeQtOr to do the same, to explicitly assign an user/resource to a Project as responsible one?
Thanks.
hello,
In global settings > planning > automation > ... you have several parameters that could correspond to your needs
auto assign responsible to activity
auto set responsible if single resource
auto allocate manager to the project
auto set responsible if needed
and auto assign responsible to activity
As a reminder : allocation for project - assignment for activity.
Hi,
Thanks for fast reply, will check all of them and see which one suits our needs the best.