Hi everyone,
I have an issue with timesheet.
On of my technician said to me he have some time on a day (sept, 22) for two activites, and he didn't do that.
I don't want to know how those two values came, i just want to delete them but cases are greyed out.
Someone have a trick ?
Posté : 30/09/2020 11:40 am
Début du sujet
ok, i forced the status of an activity from "running" to "backlog", and reverted the action.
The timesheet for this activty is now available.
Solved