The most common for this "warning" is that you defined allocation end date for resources, and they still have more work to do than open days exist till their departure from project.
Removing end dates on project allocation will remove the warning.
Posté : 17 Août PM 19:088
Début du sujet
Thank you very much this resolve the warning.