Forum

[SOLVED] Handled, d...
 
Notifications
Retirer tout

[SOLVED] Handled, done and closed dates disappear

3 Posts
2 Utilisateurs
0 Reactions
2,398 Vu
(@mcanuto)
Posts: 183
Active Member
Début du sujet
 
[#5618]

Hello, everybody.

I have a problem when I reopen an activity or a project: the handled, done and closed dates disappear .
For the closed date I can understand, but why the other two dates also disappear?

I'm forced to memorise them to retype when I reopen the objet.
Is it the normal behaviour?

I tried it in a version 6.3.5 but also in démo version (7.3.1).

Best regards,
Maria


 
Posté : 13 Déc AM 11:1212
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

It all depends on configuration of status "reopened"
On default configuration, "reopened" is a status that is "not in progress" and "not done".
So handled (in progress) and done are unchecked and dates are cleared.

To preserve handled and done dates, just check correspondong macro status on status "reopened"


 
Posté : 13 Déc PM 12:1212
(@mcanuto)
Posts: 183
Active Member
Début du sujet
 

Thank you

just another configuration I didn't know.

I've tested and it works just fine.

Regards,
Maria


 
Posté : 13 Déc PM 12:1212
Share:
Retour en haut