Hi.
Is there a way to import all Project relevant dates? I am missing all planned dates, neither of them is described or accepted in Project import structure.
Hello,
Yes, I saw those dates and I am able to import them, thanks.
But I would like to import planned start date and planned end date.
Currently, when I import done date, it is inserted in planned and real end date fields and I cannot show proper project history.
Am I doing something wrong?
You cannot imports dates that are calculated by projeqtor : planned, real, reassed
Take also into account that valaidated and left may be changed but may be consolidated from children.
Aha, sure, clear :).
As I am still novice in ProjeQtOr, I need a lot of its rules and processes to learn.
Thanks.