Hi all,
I am accessing directly the database to be able to create specific reports.
I could identify easily tables for Projects, Customers, Resources, Activities and Tickets but I did not find the table in which is stored the work by date and resource for a ticket.
Can you please indicate the table and the way to link it with the corresponding ticket.
It is table "work"
Thank you!
I have 2 subsidiary questions :
- Is the table work also used for activities?
- What is workelement used for?
- Is the table work also used for activities?
Yes, for all real work, whatever the way to enter it
- What is workelement used for?
It is a summary of all work entered by all resources on the ticket