Hi Babynus,
Could you explain me how do you calculate your margin on the project view? And what is the impact on the margin when the task is reassessed?
Regards,
Margin (in days) = Validated Work - Reassessed Work = Validated Work - ( Real Work + Left Work)
Margin (in%) = (Validated Work - Reassessed Work) / Validated Work = (Validated Work - ( Real Work + Left Work) ) / Validated Work
Margin > 0 means reassessed is smaller than validaded (you do it well and work faster than initialiy planned)
Margin < 0 means reassessed is bigger than validaded (you use more work than planned, possibly this will have impact on delays)
Thanks for reply