Hi Babynus,

Could you explain me how do you calculate your margin on the project view? And what is the impact on the margin when the task is reassessed?

Regards,


 
Posted : 04 Nov 2015 13H12
(@babynus)
Posts: 14952
Member Admin
 

Margin (in days) = Validated Work - Reassessed Work = Validated Work - ( Real Work + Left Work)
Margin (in%) = (Validated Work - Reassessed Work) / Validated Work = (Validated Work - ( Real Work + Left Work) ) / Validated Work

Margin > 0 means reassessed is smaller than validaded (you do it well and work faster than initialiy planned)
Margin < 0 means reassessed is bigger than validaded (you use more work than planned, possibly this will have impact on delays)


 