Hello I would like to do a manual scheduling for telephone maintenance for a resource. When I allocate 0.5 hour on Monday for example it automatically schedules me 4 hours. I don't understand how it works. Could you explain to me, the idea is to have a line for a phone activity on the monthly schedule and assign 0.5 hour slots to resources and no more. is it possible ?


 
Posté : 21 Jan PM 18:011
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

What you try and do is not Project Management, and will difficultly fit in ProjeQtOr.
Manual planning only books half days. You won't be able to define hour-timeslots, nor half-hour-timeslots


 