Hello,
Why doesn't the planning reports, as monthly planning project/activity/resource, show any planned work? However, there are planned work in the Gantt.
regards,
Drubs2010.
Bonjour,
Pourquoi les états de planning, tel que Planning Projet/activités/Ressources, ne montrent pas le travail planifié? Pourtant, il y a du travail planifié sur l'état du Gantt.
Cordialement,
Drubs2010.
Hi Drubs,
in my report it shows planned work. Did you run planning? Planning figures are italic and colored different.
Regards,
Klaus
Thanks, that's it.
It's because I checked fix planning in the project. I unchecked it, but it wasn't enought, I had to run planning even if I did it before the check. Is that clear?
Conclusion : When we uncheck fix planning, we must run planning.
Regards,
Drubs2010.
Hi Drubs2010,
I'm really please I could help you. Just let me add to be excact:
- If planning is fix, then no replanning will be done.
- If you didn't run planning before fix the planning, then there will be no planning values - hence they are not displayed as plan value.
I hope this enlightens things.
Regards,
Klaus