Hi,
Yesterday I uploaded and calculated my 1st planning inti ProjeQtor, by putting "Mode de planification" 1 into the Activity mass import tempate.
Then It calculated it by ordering activities next to the order following WBS breakdown (end dates) and not the start dates.

How can I arrange that?

What it the parameter or the function that manages it.

thanks & regards,


 
Posté : 11 Juin PM 12:066
(@julien-gahon)
Posts: 20
Active Member
Début du sujet
 

I solved my issue by marking activities out of the planning calculation.


 
Posté : 11 Juin PM 18:066
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

Projeqtor calculates a Capacity planning and does not take care of Start Date, unles you use planning mode "not start before validated start date" or "regular between dates".
And to order planning, it uses dependencies and priorities of activities. Defaut activity priority is WBS order. That can explain the result you get.
Just order tasks in the WBS the same order you want them to be treated to get what you expect.


 
Posté : 11 Juin PM 19:066