Hi projeqtor team ,
The default calendar concept is presently attached to resources, it would be interssed to study the possibility to be able to link also project to a default calendar , this is important for displaying the days off in Gant diagram and reports with gray colors like Week end days.
Thanks
There is default calendar, and it is used to display off days in planning view.
But it is common to all projects, as it is dedicated to store all national off days, which should be the same for all projects.
Moreover, it would not solve to select a calendar per project, as several projects can be displayed in the gantt view.
Hi Babynus ,
regarding quote :
There is default calendar, and it is used to display off days in planning view.
==> in projeqtor , How can we configure the default calender for all project ( to see days off in planning view) ?
Thanks
default calendar is first one (with ID=1)