[SOLVED] Rate allocation

2 Posts
2 Users
0 Reactions
2,692 Views
 PAD
(@apad)
Posts: 16
Active Member
Topic starter
 
[#5499]

Hi

I'm playing with Rate Allocation on projects and Rate assignment on activities.
I'm wondering if Rate is only an information about availability or if Rate is used by planning calculation ?
If Rate is used by calculation, can you explain how ?

Regards


 
Posted : 23 Oct 2018 18H03
Gautier
(@gautier)
Posts: 207
Active Member Admin Registered
 

Hello,

Yes, rate is used by planning calculation.
You should read "Allocations section" and "Assignment section" in our user guide, press F1.


 
Posted : 23 Oct 2018 18H23