Hello,
I have some resources working in part-time : they have each wednesday afternoon for themself.
I read some posts and find the way to define resource in part-time using calendar, but it seems to be only for 1 day off. In my case, the resources are 1/2 day off each week.
Is it possible to define calendar (or other method) with only 1/2 day off each week ?
Best regards !
Paul-Henri
Hello
Unfortunately ProjeQTOr does not manage part-time from calendars.
To record Wednesday afternoons of these resources as not worked, you will need to record absences.
choose half day in duration and indicate Wednesdays as recurrence or enter a period between two dates.
Upon validation, all Wednesdays from the current date or between the two dates will be marked with a half day of absence
Hello,
Thank you for your answer. I will try to manage this through the absence sheet.
Best regards!