Hi,

My resources are not prioritized for some tasks, for example, a recourse has 30 h work on Task A with priority 400, and another task B with priority 600 which is a very project and takes months to finish. When I do the planning he will start Task A for one day then do Task B, then after that finish Task A.

It's very frustrating, I don't know what I did wrong and where I can check to do the adjustments.

Thanks in advance!


 
Posté : 26/08/2019 2:15 pm
(@babynus)
Posts: 14952
Membre Admin
 

Be sure to replan both projects at the same time.
If you replan only one project, availability taken for the other won't be changed.


 
Posté : 26/08/2019 5:31 pm
 Moqi
(@clarezoe)
Posts: 73
Estimable Member
Début du sujet
 

OK. That's why, thanks!


 
Posté : 27/08/2019 5:09 pm