[SOLVED] Sum
 
Notifications
Clear all

[SOLVED] Sum

3 Posts
2 Users
0 Reactions
2,263 Views
(@yannobi)
Posts: 69
Active Member
Topic starter
 
[#5553]

Hello

What can explian that there is a difference between the "Work to do", and the "Assigned + Real Work"

As a Project Manager, i didn't change the value in "Work To do".
If you have an idea !!!


 
Posted : 14 Nov 2018 14H50
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Left work can be updated on Timesheet by resource
Check history of activity to see what was done


 
Posted : 16 Nov 2018 1H44
(@yannobi)
Posts: 69
Active Member
Topic starter
 

Exact. I found the guy 😉


 
Posted : 16 Nov 2018 17H20