[SOLVED] Tickets / activités/jalon lié à un projet

5 Posts
3 Users
0 Reactions
2,775 Views
(@rmiroff)
Posts: 50
Active Member
Topic starter
 
[#6964]

I am in version 8.5.3 and I have created many projects with milestones and activities

I do not find the milestones and activity in the "links" section of my projects

Why?

Thank you


 
Posted : 02 Oct 2020 1H18
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI

What do you mean by Links, where ? which screen ?

Thanks


 
Posted : 02 Oct 2020 11H14
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Because your milestones and activities are not "linked" to the project, they are "contained" into the project.
You will use link to link projects between them, or link a ticket from support project to a new project to point out that this ticket was the origin of the project.


 
Posted : 02 Oct 2020 11H26
(@rmiroff)
Posts: 50
Active Member
Topic starter
 

Can we automatically link an action, a milestone, a ticket for a project?
Because on the first window of my project I cannot know if an activity or a milestone or an action is in place.
I have to go to each section to see if my project is concerned.


 
Posted : 27 Oct 2020 18H10
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You have the information on "Today page", with a summary.
Or you can use "global view" screen to see main objects on a project (using project selector)


 
Posted : 28 Oct 2020 17H45