Hi,
I wish to allow my coworkers to mark some days as teleworking to share with the team.
I am not sure what the best practice would be for that. I am thinking of using a special task within an "internal project", with manual planning, and use the interventions feature.
But wouldn't that mark the resource as occupied ?
What is the best practice to handle a teleworking status, without impacting the availablity of a resource ?
Thx
Franck
Hello
But wouldn't that mark the resource as occupied ?
no, you can indicate intervention methods without planning work on these dates.
What is the best practice to handle a teleworking status, without impacting the availablity of a resource ?
For the moment, this is the only solution that is possible.