a team member is assigned to a sub-project, but not to the “parent” project. Is it normal that he does not see the project for which he is assigned?
to avoid "polluting" it, it is not desirable for it to be assigned to "parent" projects
HELLO,
Yes he is not allocated automaticaly on parent project. you have to do it . On the other way from parent to sub project is automaticaly.
BYE
Sorry, Hello...![]()
It's not possible to just see the sub project, without the parent project ?
it should be like that !!! it is weird.
The behavior is like expected.
If you have project P1, with sub-project P1.1, you can allocate user/resource to P1.1 only.
Then user sees items of P1.1 only, as if P1 does not exist.
Pleas post screenshots of your settings (project structure, allocation)