Hi
I have two cyclic tasks (planification mode: regular between two dates) to go down the bandwith of my ressource because he is not working on project at 100% (aprox. 50%) , but sometimes I need to create a task which it takes the 100% of the bandwith, I tried to increase the % affectation (on task and project) above 100% but it is not working.
Anybody knows a workaround ?
Thanks
Change planning mode.
Regular between dates will regularly dispatch the assigned work during the period. So unles you define work exactly equal to suration x capacity, you won't get expected result.
Thanks Babynux,
I can't change it because I choose this planification mode because this ressource is not working at 100% on projects but sometimes, we have an exception that's why I asked it.