Start/End Date update

4 Posts
2 Users
0 Reactions
1,679 Views
(@julien-gahon)
Posts: 20
Active Member
Topic starter
 
[#6751]

Hi,

Using a CSV import template, I uploaded yesterday activies, some of them contains Start/End Planned/Validated Dates. Finally everything has been recorded with 09/05/2020.... This morning I updated dates into each corresponding activities but it didn't udpate the planning view.

Attached the Template in xlsx.

Could you help and explain me what is going on? Where did I do errors?

Thanks very much.
Julien GAHON - Dietsmann


 
Posted : 10 Jun 2020 14H31
(@babynus)
Posts: 14952
Member Admin
 

After importing activities, you must go to Planning view and execute planning calculation (gear button)
Planned dates are not imported as they will be calculated by the tool.


 
Posted : 10 Jun 2020 15H04
(@julien-gahon)
Posts: 20
Active Member
Topic starter
 

It calculated by modifying original start dates with new ones following "next to the other activities end" of the WBS.

I need it plans with the original start dates I put.

How can it manage that?
Regards,


 
Posted : 10 Jun 2020 17H14
(@babynus)
Posts: 14952
Member Admin
 

Set planning mode "do not start before validated start date", enter expected start date as validated start date (not planned start date that won't be imported and systematically changed by planning calculation) and import activities in the order of start date so that they have WBS in same order.


 
Posted : 12 Jun 2020 9H49