Hello,
I am new in this projectorria, before I was using phprojekt.
I need to know step by step of creating new project in this application ?
For example:
Project name = project_a
Start date = 1 october 2012
End date = 31 october 2012
Project leader = user_pl_a
Project member = user_pm_a, user_pm_b
Project Quality member check = user_pq_a
Task
============
1. users management (eta 4 days)
1.1 create user view function (1-2 october) (worker: user_pm_a)
1.2 create user add function (1-2 october) (worker: user_pm_a)
1.3 create user edit function (2-2 october) (worker: user_pm_a)
1.4 create user del function (3-4 october) (worker: user_pm_a)
2. product management (eta 2 days)
2.1 create product view function (5-5 october) (worker: user_pm_a)
2.2 create product list function (5-6 october) (worker: user_pm_a)
3. main home (eta 28 days)
3.1 create top block function (3-30 october) (worker: user_pm_a, user_pm_b)
3.2 create left block function (3-10 october) (worker: user_pm_a, user_pm_b)
3.2.1 create user stats function (7-10 october) (worker: user_pm_a)
3.2.2 create visitor function (10-10 october) (worker: user_pm_a)
3.3 create right block function (5-25 october) (worker: user_pm_a)
3.3.1 create red function (5-5 october) (worker: user_pm_a)
3.3.2 create blue function (5-7 october) (worker: user_pm_a)
3.3.2.1 create blue green function (6-7 october) (worker: user_pm_a)
3.3.2.2 create blue green yellow function (5-6 october) (worker: user_pm_a)
3.4 create bottom block function (27-31 october) (worker: user_pm_a)
4. quality test control (eta 3 days)
4.1 quality test user management task (28-30 october) (worker: user_pq_a)
4.2 quality test product management task (29-31 october) (worker: user_pq_a)
4.3 quality test main home management task (30-31 october) (worker: user_pq_a)
How to implements above example in projectorria ?
I'm using version 2.6.1
Thank you
Web Hosting and Server Provider
============================
Web Site: http://www.jfoc.net
Project name = project_a
Start date = 1 october 2012
End date = 31 october 2012
Project leader = user_pl_a
Project member = user_pm_a, user_pm_b
Project Quality member check = user_pq_a
Create new project project_a.
Create resource user_pl_a, profile project_leader, default function manager (or new one you want to create).
Create resources user_pm_a, user_pm_b, profile project_member
Create resource user_pq_a, with new profile you can create (of maybe supervisor will fit)
Affect all there resources to the project project_a.
Task
Create activities and sub-activities (specifying parent activity), and assign the corresponding resource to the activity, with some assigned work.
You can also specify dependencies between tasks (prédecessors and seccessors). For instance you can define a start milstone, prior to all parent tasks, to define start of project.
Then go to planning screen and run planning, and adjust constraints and work to get what you want.
Regards.
Project name = project_a
Start date = 1 october 2012
End date = 31 october 2012
Project leader = user_pl_a
Project member = user_pm_a, user_pm_b
Project Quality member check = user_pq_aCreate new project project_a.
Create resource user_pl_a, profile project_leader, default function manager (or new one you want to create).
Create resources user_pm_a, user_pm_b, profile project_member
Create resource user_pq_a, with new profile you can create (of maybe supervisor will fit)
Affect all there resources to the project project_a.
how about the task ? create from 'activity' ?
Best Regards,
Web Hosting and Server Provider
============================
Web Site: http://www.jfoc.net
I completed previous post.
(clicked on submit too soon 😉 )
One point is interesting me : why do you consider migrating from phprojekt to Project'Or RIA ?
One point is interesting me : why do you consider migrating from phprojekt to Project'Or RIA ?
I saw that Project'Or RIA has many features that phproject doesn't have, which are good to have everything in one application.
Web Hosting and Server Provider
============================
Web Site: http://www.jfoc.net