Task the same day with predecessor element

3 Posts
2 Users
0 Reactions
6,508 Views
 Alex
(@kiffcool)
Posts: 16
Active Member
Topic starter
 
[#379]

Hi !

I create one projet named "ProjetA1".

I create one task named "Planning".

I create two tasks named "Rédaction Planning" and "Validation Planning" with parent activity "Planning".

The two tasks must be done the same day (the 22/02) :
- "Rédaction Planning" : 0,5 day
- "Validation Planning" : 0,5 day (with the predecessor element "Rédaction Planning")

In the planning, when predecessor element is active, it’s impossible to do the two tasks in the same day (0,5 + 0,5 = 1 day).

Why ???


 
Posted : 24 Feb 2012 17H53
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

Because dependency will alway define [start day of task 2]=[start day of task 1]+1
No matter the work : dependencies is set to force start of task 2, even if they are not assigned to the same resource.
It's because there is no "time" on tasks start / end dates. So when a task ends day X, next will start day X+1, even if the first task end mid-day.

If you wish to plan small tasks one after the other, and that these tasks are assigned to the same resource, you don't need to set a dependencies.
Just order them the way you'd like them to be planned.
Or you may also set priorities to be sure to plan them in the good order.

Regards


 
Posted : 25 Feb 2012 17H31
 Alex
(@kiffcool)
Posts: 16
Active Member
Topic starter
 

OK, thank you.


 
Posted : 27 Feb 2012 12H29