Teams are not working at fully time on project 4

7 Posts
2 Users
0 Reactions
6,953 Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#2720]

Hi all

I explain my doubt; I have one cyclic task (planification = regular between two dates) (70% of a day time) and the other 30% are dedicated to all projects.

For example, for one ressource, I have 4 projects. So, how can I assign the 30% for these 4 projects?

My solutions are:
- 30% / 4 = 7.5% ressource affected on each project (problem: what's happen if today, I have 6 projects, I need to update all my affectations?)
- 30% on all activities ???

My two solutions are not optimal, do you have a better solution?

Thanks


 
Posted : 10 Nov 2015 19H16
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Any idea?


 
Posted : 12 Nov 2015 14H54
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Any idea? :blush:


 
Posted : 16 Nov 2015 12H09
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

I would set 100% to all projects...
They it is priorities, dependencies that will define when projects are planned.


 
Posted : 16 Nov 2015 19H54
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

100% or 30%??? because my bandwith for project is only 30%


 
Posted : 16 Nov 2015 19H58
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

100%
Yes
I confirm 100%

Regular between dates will be planned first (it is one of the priority rules for planning) and other projects will only use left availability, so affectation rate at 100% will use the 30% left.


 
Posted : 16 Nov 2015 20H43
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Excelent news, easier to plan for me.

Thanks


 
Posted : 17 Nov 2015 11H37