Hello,
I would like to know if it is possible to input the timesheet in hours and not in days unit.
On the basis of 8 hours equal 1 day.
Thanks in advance for your answers
Best regards
Yes, it' possible.
Just go to global parameters screen.
You'll be able to set work unit for real work allocation, work unit for activities and number of hours per day.