Hello,
I lost the ability to display Activities on the Planning tab within ProjeQtor.
I created a new Project and added Activities. Normally, the Activities would appear on the Planning tab. It no longer does.
I can view Activities for older projects but not for new projects. And new Activities appear on the Planning tab for existing projects but not for new projects.
Thoughts? Help!
v5.2.4
Thanks, paul
What is the type of youhr new project ?
Administrative ?
Thanks for your reply.
Yes, the project type is Administrative. Is there something special about that project type? Meaning, this is a feature not a bug? 😉
Thanks for your patience. I’m a ProjeQtor newb.
-paul
Yes, administrative projects are not displayed in hte Gantt planning view.