Forum

Update of field pro...
 
Notifications
Retirer tout

Update of field progress on a project

2 Posts
2 Utilisateurs
0 Reactions
5,341 Vu
Cassano Gabriele
(@gabriele)
Posts: 17
Active Member
Début du sujet
 
[#5102]

Good morning,

I have a question about the update of field progress on a projet : I have make test to know how update manually or by following a parameter, to update this field, but this field is only updated to only "100%" when I change the status to "done", "verified", "validated", etc.
Could you explain me how does it work to set this field ? I think he is not used only to display "100%" when the project is done, I need to display for sample, "50%" if the projet is in progress.

Thank you in advance.

Yours.

Gabriele Cassano.


 
Posté : 26 Avr AM 11:044
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

We have two progress Data :

  • first one in Progress section displays "real" progress, corresponding to real work.
    To have it calculated, you must enter assigned work on activities, then enter real work and possibly update left work
  • second on is directely entered on the project by project leader
    It is just an estimate from the project leader
    Values are numeric, but it is just display, you can change it in parameters and have textual values (not started, started, almost finishzd, ...)

 
Posté : 26 Avr PM 13:044
Share:
Retour en haut