[Hi,
i'm facing with the folowing.
I have filled a task with validated date, but the teask still in brown color, and the planned date is postponed with more days.
I can understand this kind of situation if I have more than one task in parralel, but in my case as shown in picture, I have only one task, or may be some task are hidden.
Best regards,
Frédéric
HI,
Please recalculate the planning.
Then if it still like that it means that your resource is not planned somewhere else.
There is no problem with this Gantt compare to dates ! Please read the friendly manual
Valided dates is a wish you have to compare with the planified dates calculated by the application with all constraints you gave to it
Projeqtor is more than a drawing tool of nicest Gantt 😉 It is a capacity planning based on workload and constraints. The planification is good or not compared to expected ( validated) dates. So your job as Project Manager has started trying to be able to keep the lead or catch up the drift using Projeqtor at any moments with your own solutions still comparing planified and expected dates on activities and/or on the project.