I know that it should hide "completed items". However, this is not enough details.
Below is what I get while the checkbox is checked:
- The checkbox hides some "done" tasks in status done in the current week and leaves some.
- Some "done" tasks progressed further in the workflow after the "done" status (ex: to "verified", "delivered" or "validated") should these get hidden by the checkbox?
- Some "done" tasks get hidden only when I move the view to the next week.
- Some "done" tasks that were already hidden when I checked the checkbox reappear when I go back to a previous week.
So, I do not understand what this checkbox actually does. I appreciate some clarification.
Hi,
Task marked as done are hiden unless some real work is entered for them on the cuirrent week.
This is a general rule : in real work allocation, all tasks with real work on the displayed week are shown, whatever the status (done, closed, cancelled, ...). It is to vbe sure to always display complete entered work for the week.
Thanks for the clarification
Task marked as done are hiden unless some real work is entered for them on the cuirrent week.
This means tasks marked at least as "done" so this includes the next statuses ("verified", "delivered", "validated"), right?
It includes all the status that will check the done flag.
And is will also include tasks where done flag is checked manually (if allowed on activity type)
Got it. Thanks a lot . :cheer: