Hello,
I asked my team to submit and validate weeks as soon as the week is finished.
But we encountered a problem : Some tickets take more than 1 or 2 weeks to be finished and when a week is validated it become impossible to add consumed time on these tickets in newt weeks.
Is this by design or did we miss a parameter to tune?
In case it is by design do you have any suggestion
Thanks in advance
Posté : 24 Juin PM 13:066
You can enter work on day other than current day with button "dispatch work"