Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

Workload reporting ...
 
Notifications
Clear all

Workload reporting per resource

2 Posts
2 Users
0 Reactions
2,295 Views
(@pierre-martins)
Posts: 5
Active Member
Topic starter
 
[#4825]

Hi,

Again, sorry if I missed something.
- I saw some interesting reports but I would like to get the ability to see the workload of one or a bunch of resources over a specific period of time.
Is that possible (Like John workload during the month) ?
- I also would like to know if there is the possiblity to get automatic warnings when the worload of a Resource exceed 100% over a specific period of time (For instance if I use this resource on 4 tasks that requires 30% of time over 1 month, I would be at 120%)

Best regards,
Pierre Martins


 
Posted : 08 Dec 2017 13H38
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Reports :
Real Work => Work for a resource - Monthly
Planning => Work plan per resource and per month
Planning => monthly planning for a resource


 
Posted : 12 Dec 2017 11H22
Share:

Scroll to Top