Bonjour à tous,
Je souhaite cloturer un travail estimé à 10h, je n'en passe que 8h, comment puis je le cloturer sans avoir à remettre le temps estimé = temps réel
Merci pour votre aide
Guens
PLEASE POST IN ENGLISH !!!
___
Set left work to zero.
Wher can i set left work to zero?
Thanks
Guens
2 ways :
- in real work allocation screen
- in activity screen, updating assignment