 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 
[#2196]

Hello,

I am trying to use this fabulous tool, also for my campaigns.

So, the idea is to do a campaign template with main/sub, activities & milestones.
As you can see on my screenshot.

I have one Project (Campaign Template)
Many Main Activities with sub activities and milestones.

I would like to only insert days (on the duration field) on all my sub activities. And a start date on the entire Project (Campaign Template). So this become a block and by accumulating the days inserted I will get a end date.

My objective is to simplify the parameters of each activities, milestones etc…
Because, the information become redundant at some point.

I tried to play with predecessor/successor/linked element, but without any success.

In the case, I can do this template, I will only need to duplicate the entire project, rename it and change the start date.

It will be awesome!!! 🙂

Ps: When I copy anything, I have “origin” fulfill with the ex name, are there any repercussion on the rest or is it just for information?

Thank you for your help,
Sincerely
Dem


 
Posté : 5 Fév PM 18:022
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

You're almost( where you want. 🙂

1) Just set planning mode to "fixed duration" for all activities (this can be done through mutiple update mode) and define duration.
2) Define a milestone with mode "fixed milstone", define date for this milstone and set it as predecessor of first(s) task(s).
3) Run planning : you're there ! B)

Another hint : when your template project is OK, define its type to "Template". This way : it will not be visible any more in the planning (as it is not a real project) and it will become visible to all project managers that will be able to copy it. :woohoo:

As you guessed it, Origin is only an informative data, without any efect on the planning.
You can avoid adding Origin, just unchecking corresponding checkbox when copying 😉


 
Posté : 5 Fév PM 21:022
 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 

Hi babynus,

Thank you a lot, I will immediately try this.
Regarding the template mode, I deleted all "projects types" and I kept only "OPE" code.

Now I am trying to re-create a type "TMP" but even as an admin I can't anymore. (gray field)
I would like also to try to manage my project with "ADM" type, which sound a lot easier regarding resource assignments.
(because, this function still a bit foggy for me)

Thank you really much for your help.

Sincerely,
Dem


 
Posté : 9 Fév PM 12:022
(@babynus)
Posts: 14952
Membre Admin
 

I deleted all "projects types" and I kept only "OPE" code

How did you do that ? :silly:
Projets Types "TMP" and "ADM" cannot be deleted :whistle:

Now I am trying to re-create a type "TMP" but even as an admin I can't anymore.

If you directly updated Database, you'll have ot do the same : insert newlines directly in Database (or insert new one with other code, and change code in database afterwards)


 
Posté : 9 Fév PM 15:022
 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 

Hello,

I didn't do anything into the database, I deleted them from the web-interface. I am really sure of that.
By the way, what is the table name for "Projects types". :cheer:

So, if I understood well. In order to have resources planning generated without waiting for the project manager to define the real work affectation.
I should use the "ADM" type?

Thank you a lot again and again 🙂

ps: Do you have a documentation about the database, i am not a technical guy and for me it is hard to find where are things.

Gday


 
Posté : 10 Fév AM 11:022
(@babynus)
Posts: 14952
Membre Admin
 

By the way, what is the table name for "Projects types".

table is type, with scope='project'

So, if I understood well. In order to have resources planning generated without waiting for the project manager to define the real work affectation.
I should use the "ADM" type?

Yes, any type with code ADM will do the job.

ps: Do you have a documentation about the database, i am not a technical guy and for me it is hard to find where are things.

No, sorry, there are no technical docs.


 
Posté : 10 Fév PM 16:022
 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 

Hi Babynus,

I found it! and modified the type. You were right of course, I didn't delete the TMP & ADM by default. I just closed them (this is the reason 🙂 ).

So I tried the type ADM on one of my project. And the project doesn't appear in planning anymore.

What I would like to do is to simply assign activities to resources. And without going trough "real work allocation" or any actions from the resources. To get the resource planning generated.

Because as far I understood, OPE type, the resources need to go to "Real work allocation" assign days or hours (I believe is day=resource capacity, but why isn't it a tick box) on days of the current week. And once he validate the work, the resource will appear in "Resource planning". So I would like to skip this.

Is it possible?

Thank you really much for your patience.

Sincerely,
Dem


 
Posté : 11 Fév AM 11:022
(@babynus)
Posts: 14952
Membre Admin
 

So I tried the type ADM on one of my project. And the project doesn't appear in planning anymore.

This is expected behavior.
AMD (administrative) and TMP (template) project are not suposed to be planned.

What I would like to do is to simply assign activities to resources. And without going trough "real work allocation" or any actions from the resources. To get the resource planning generated.

ADM projects are not planned. Only real work is entered(it is what they are done for).
You can use Activities screen to create assignment to resources, but :
1) you would have to affect resource to project before
2) you really don't need this because it is not how ADM projects work.


 
Posté : 13 Fév PM 15:022
 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 

Hello,

Is it possible to have the same behavior as "OPE", Except the fact when someone allocate some tasks to a resource, it is count as "real work allocation" automatically without any confirmation of the resources.

Thank you,

Sincerely,
Dem


 
Posté : 20 Fév PM 12:022
(@babynus)
Posts: 14952
Membre Admin
 

No, it's not possible.
This is completely opposit to ProjeQtOr philisophy.


 
Posté : 20 Fév PM 12:022
 stef
(@dem)
Posts: 14
Active Member
Début du sujet
 

Ho ok ok!

I don't want to disturb the philosophy 🙂
I though it was only a step in the entire process and that there is a solution to skip it. :silly:

So I will try to understand better how it is working. Because it still foggy for me.

Thank you again.
Wish you a great day and mostly weekend.


 