Hi Team,

In Planning Screen, When I am going to add dependency in some activities at that time I am feeling helpless that it is not showing wbs. Due to that, I just need to change the activity name which I don't want.!
If this feature (show wbs too with activity id) will be added while adding dependency it will be Good.

Thanks.


 
Posted : 11 Apr 2022 10H34
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

In the pop-up, biside list of activities, click on the "search" button (magnifyer icon)
You'll be able to see wbs in the list


 
Posted : 11 Apr 2022 13H38
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Thanks for reply.
I have tried as you suggested but it is not showing any wbs in that list. Please find attachment for reference.


 
Posted : 11 Apr 2022 14H42
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You need to add the WBS columns on activity screen befor opoening the pop-up


 
Posted : 11 Apr 2022 15H54
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

I am already doing so, but it is not showing wbs in help!. Please find attachment for reference.


 
Posted : 11 Apr 2022 16H26
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You display WBS in Gantt view, noty is Activity view (look for Activity screen)


 
Posted : 11 Apr 2022 16H49
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Thank you So much,

It worked. I will change my practice.


 
Posted : 11 Apr 2022 16H57