Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 
[#408]

Hi,

I think it will be great to have Change Request in the Work group. It should be linked to project and the task (similar to Ticket). I can supply more information about fields required if you decide to implement it.

Regards,
Evgueni


 
Posted : 09 Mar 2012 12H39
(@babynus)
Posts: 14952
Member Admin
 

Hi,

A Change Request is a ticket.
You just have to define the ticket type to have it work !


 
Posted : 09 Mar 2012 12H54
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

No quite - there is no link to the document unfortunately and it actually required a task already created to link it with...
Regards,
Evgueni


 
Posted : 09 Mar 2012 13H04
(@babynus)
Posts: 14952
Member Admin
 

Sorry, I don't understand...


 
Posted : 09 Mar 2012 13H07
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Ok, Change Request document need to be created and approved - this can be done using documents approval process which I believe is coming soon.
When we create a Change Request (Ticket?) it need to be linked to this document as a source/reason or have it own approval system (less satisfactory). CR document should have not only pure request but an information, analysys, and approved by designated people.
Ideally Change Request (Ticket?) should become a task in the project or need to generate the task which need to have resources, etc.
Hope this make it more clear.
Regards,
Evgueni


 
Posted : 09 Mar 2012 13H15
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

One of the possible solution is to add a document to the type of origin, so document can be origin for ticket or/and task


 
Posted : 09 Mar 2012 13H28
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Evgeni,

we have following:

Change request is defined by us as a change on existing system or new request -- but not a indicent. We put in the requestor and attach if available a document. Changes always handled with Activities, because we have to have a estimation on time, costs and qualtiy before approval -- which is not available on Tickets. Approval is done by status. Date and work is entered in validated. In the case, an incident or a risk is source of change request, we link the Ticket or Risk, Action, Meeting, Decision, ... as origin.

Klaus


 
Posted : 11 Mar 2012 20H20
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thanks Klaus, but I would say this is kind of way around rather than solution. Change request can be raised by different ways and it need to be dealt with in consistent way - Initial CR document itself with description, estimates, etc. need to lead to a Ticket wich should have an aproval process by the different people before Activity will be created (can be rejected as well). Actually Ticket needed to link CR document to the Activity (if approved) or just keep it (in case of deferred) for future, or close it if rejected.
Regards,
Evgueni


 
Posted : 12 Mar 2012 11H07
(@babynus)
Posts: 14952
Member Admin
 

Maybe V2.1 will help :
- A document can be an Origin
- Planned Work for ticket

Regards.


 
Posted : 12 Mar 2012 12H33
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thanks - this definitely will help
Regards,
Evgueni


 
Posted : 12 Mar 2012 13H30
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Babynus,

if you add planned work, it would be welcome, if it is in the same manner as on Activities - requested, validated, planned, real -- for Date and work.

Klaus


 
Posted : 12 Mar 2012 14H23
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Yes, I think everybody would like it this way! Will become very useful feature!
Regards,
Evgueni


 
Posted : 12 Mar 2012 14H46
(@babynus)
Posts: 14952
Member Admin
 

Hi,

I did not plan it this way, for one sinple reason : tickets are not planned elements.
If you wish to have tickets planned, then just use Activities (new activity type for instance).

I plan to add (well in fact it is already done) : "estimated work" and "real work".


 
Posted : 12 Mar 2012 15H19
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Fine with me.

Klaus


 
Posted : 12 Mar 2012 15H41
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

As soon as it can be originated from the CR document and have a link to task - fine with me as well
Regards,
Evgueni


 
Posted : 12 Mar 2012 15H43