Hi,
In activity main screen, the task duration is an integer of days. Would it be possible to make it decimal ? As it is possible to assign a decimal duration to a resource, it would be coherent to define a task duration as a decimal.
Thanks & best regards.
Posté : 21 Oct PM 16:1010
No, it's not, and has small interest as projeqtor does not manage time.
Duration is just the difference between start and end date.