Hi,

At present time, when I assign a pool to an activity, and ask for a unique resource, projector chooses one resource in the pool when calculating the planning, and it is possible to make it definitive in the activity assignment view. It would be very usefull in the same way for a given activity to exclude some resources of the pool. This is actually to take into account resources skills and prevent some resources to be assigned activities for which they are not eligible. Though, I want to use the biggest pool of resources as possible to let projeqtor compute good schedules. It is worse to define several pools because one resource cannot belong to several pools.
Without this feature, I am obliged to force a non optimal resource assignment and exclude the activity from the benefits of pool use.

A better solution but which would be a bigger change, would be to be able to define skills and level of skills for resources, and skills requirements for activities.


 
Posté : 04/12/2023 12:13 pm
(@babynus)
Posts: 14952
Membre Admin
 

 exclude some resources of the pool

May be interesting, but very specific, and very very complex to implement.

A better solution but which would be a bigger change, would be to be able to define skills and level of skills for resources, and skills requirements for activities.

Do you mean skill management ?
 

 

with skill of resources ?
 

with search by skill and availability ?
 

with skill for acttivity ?
 

with search for allocation from skills ?
 

 


 
Posté : 04/12/2023 1:46 pm
(@brasal)
Posts: 52
Trusted Member
Début du sujet
 

Thanks, I did not activate this module. This is very helpfull. Does the schedule engine take into account this information when choosing resources from a pool?


 
Posté : 04/12/2023 5:34 pm
(@babynus)
Posts: 14952
Membre Admin
 

No


 
Posté : 04/12/2023 6:17 pm
(@brasal)
Posts: 52
Trusted Member
Début du sujet
 

Is there a chance it could integrate the roadmap for assignement of pools, teams or organizations?


 
Posté : 04/12/2023 6:37 pm
(@babynus)
Posts: 14952
Membre Admin
 

No sure, possibly not unless it is sponsored... and completely specified.


 