Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi,
1) In imputation view : Do not display activities if they are in the "Recorded", "Copied" ?
2) When assigned one resource status change. Transition to "assigned" automatic
3) Ref documents: I'd like to add the version and revision. Possible?
4) Other evol : Today => Store documents by type, Evol => Add one or several "directory project" (with code projet) in "directory type". Easy to follow.
Thanks
In imputation view : Do not display activities if they are in the "Recorded", "Copied"
Why not, but it should be optional, to have choice to display or not these activities.
why not the propose to hide status done or over ? ...
Ticket #888 registered
Difficulty behind the request is that status list is updatable... these status can be changed or deleted or replaced
When assigned one resource status change. Transition to "assigned" automatic
Today, reverse behavior exists as a control : mandatory responsible on assigned status.
Ticket #889 registered.
Like above difficulty is that list is updatable... Several status can be considered as "assigned" status.
Ref documents: I'd like to add the version and revision. Possible?
No, not on Reference : the reference of a document must not change throught the document lifecycle.
Request #768 seems similar to this one.
Other evol : Today => Store documents by type, Evol => Add one or several "directory project" (with code projet) in "directory type". Easy to follow.
You can do it right now : when you manage directories, you can define the project for the directory.
Existing directory structure is defined to store one type on one directory, but you can manage it the way you like, for instance with one top directory for each project ..
Why not, but it should be optional, to have choice to display or not these activities.
why not the propose to hide status done or over ? ...
Ticket #888 registered
Difficulty behind the request is that status list is updatable... these status can be changed or deleted or replaced
Very good idea. We propose a list of state we desired to be masked.
Same management as "show closed items"
Today, reverse behavior exists as a control : mandatory responsible on assigned status.
Ticket #889 registered.
Like above difficulty is that list is updatable... Several status can be considered as "assigned" status.
I understand if the condition below is "assigned", toggle the state of the activity "assigned"
You can do it right now : when you manage directories, you can define the project for the directory.
Existing directory structure is defined to store one type on one directory, but you can manage it the way you like, for instance with one top directory for each project ..
How is it that the documents be stored in the directory "code project"?
My need: Storage product and project in a directory with project code
Thank you
Let say you have document root is $DOC.
You have Project A, code AAA and Project B, code BBB.
You define directories this way :
1) /AAA, name Project A, linked to Project A
2) /AAA/sub1, name sub1, linked to Project A
3) /AAA/subN, name subN, linked to Project A
4) /BBB, name Project B, linked to Project B
5) /BBB/sub1, name sub1, linked to Project B
6) /BBB/subN, name subN, linked to Project B
and so on.
Dear all,
let me chip in following perspective:
When assigned one resource status change. Transition to "assigned" automatic
We didn't have status assigned and we wouldn't have this automatically set to any status, because our workflow works in an other way.
In imputation view : Do not display activities if they are in the "Recorded", "Copied" ?
Good idea. It would be helpful to select which status should not be displayed, because we have other/individual statuses.
Klaus
Thank you
Another idea: The option "sending e.mail" proposes : requestor, responsible, team ...
Is missing the possibility to send all resources assigned.
Thanks
It is request of ticket #907