Could we add to the planning and global planning view, so a person can see the validated dates start and end date as well as the planned start and end date, so they can see when orginally an activity was agreed (validated) to be done. It would be make visibiliy impact of auto planned changes easier to see. Going into each activity is not always possible or practical.
Thanks
Bev
This is purpose of baseline.
When your planning is validated :
- save validated dates (this will copy planned dates into validated dates)
- save baseline V0 (this will "copy" gantt)
Then you'll be able to display baseline V0 showing validated dates
Thanks Babynus,
We know this is possible to do now it has been fixed and you can see graphically in blue the old plan and the current planned gantt chart together. But it would be very helpful to be able to see the validated dates in the table of data, as it is easier to see data this way sometimes and sort.
Thanks Bev
Request recorded as Ticket #4155