Hi,
In Italy we can request a leave period ranging from one hour to several hours (1-8), not just in multiples of half days as managed in ProjeQtor.
Is it possible to change the standard behavior?
Hello,
This is not an evolution since it's already possible in ProjeQtOr for a long time.
You can manage the work unit in Global Parameters/Work Time, as explained in the manual and on this screenshot.
Have a nice day !
The HR Leave Management modules can manage only half days.
But you can define administrative project, with activities that wil lbe the day off.
Then you can record real work in the future or use screen "absences" to record leave days or hours.