Hello,
when using manual progress of fixed-duration activities, meeting duration can't be used and charge for meeting is not computed because if you set left work to 0 for meeting, no work is computed on project and, also, you need to set left work individualy and it could be a long job if there is a lot of attendees.
To get around this behavior, we didn't set the end time for meeting, so assigned work is 0 and, when meeting is done, left work is also 0.
Is it possible to set a new behavior for meeting so, when meeting is set to done, real work is set to assigned ?
So, charge for project will be set correctly and, most of all, it will be usable to set end time for meeting.
Hope to be clear,
Regards,
Request recorded as Ticket #5275