when modifications are needed on the general calendar (for example the calendar of the enterprise), we have to click on the button "importer cette année à partir du calendrier" for each calendar of the employees
we can imagine a general export for all calendars
It is because calendars should not be defined for each resource.
You should not think 'like in MS-Project".
ProjeQtOr provides the "Administrative projects" mecanism to record off days for single resource.
I think not understand the mecanism ....(maybe too late) 😉
i dont understand.the term "adminitratives projects"
could you precise the mecanism...
Here are some references :
https://manual.projeqtor.org/html_en/ListsOfTypes.html?highlight=project#projects-types
http://www.projeqtor.org/fr/forum-fr/3-propose-evolutions/7657-time-bounded-assigning-to-calendars#14931
http://www.projeqtor.org/fr/forum-fr/5-ask-questions/7465-usage-of-admin-project#14349
http://www.projeqtor.org/fr/forum-fr/5-ask-questions/7286-absence#13927
http://www.projeqtor.org/fr/forum-fr/5-ask-questions/7135-about-admin-project#13382
Thanks you for explanations