Recalculation Auto

18 Posts
2 Users
0 Reactions
11.3 K Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#2770]

Hi

It could be a good idea to have a check box to recalculate automaticaly the planning after any update. I think this check box could be useful at project level.

Thanks


 
Posted : 30 Nov 2015 17H24
(@babynus)
Posts: 14952
Member Admin
 

This button already exists in the planning view.
Can be used for instance when you build your project.

To have global calculation on each change, it is a bit more complex than a single button.
But request already exists : Ticket #1815


 
Posted : 01 Dec 2015 10H23
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

This button already exists in the planning view.
Can be used for instance when you build your project.

Could you give me more detail about this way?

To have global calculation on each change, it is a bit more complex than a single button.
But request already exists : Ticket #1815

No doubt it is not easy :silly: Your work and your project is awesome.... Thanks again for your help


 
Posted : 01 Dec 2015 11H36
(@babynus)
Posts: 14952
Member Admin
 

Could you give me more detail about this way?

Just go to the planning view, check the checkbox "automatic run plan" and make any change on activity. You'll see what happens.


 
Posted : 01 Dec 2015 12H43
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Could you give me more detail about this way?

Just go to the planning view, check the checkbox "automatic run plan" and make any change on activity. You'll see what happens.

I'm working on v5.0.6, is it enable? because i didn't found it.


 
Posted : 01 Dec 2015 17H27
(@babynus)
Posts: 14952
Member Admin
 

No.
New on V5.1


 
Posted : 01 Dec 2015 17H31
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

That's why I didn't found it. :woohoo:

More arguments to upgrade 😉


 
Posted : 01 Dec 2015 17H40
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Hi Babynus

I want to recalculate automatically the planning every day, I want to use a script, could you send me the function which it is call to recalculate the planning to add it on my own script.


 
Posted : 03 Dec 2015 15H26
(@babynus)
Posts: 14952
Member Admin
 

The function to call is PlannedWork->plan()


 
Posted : 03 Dec 2015 17H05
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Thanks, without argument, I suppose that this function recompile planning for all projects, is it correct?


 
Posted : 03 Dec 2015 18H42
(@babynus)
Posts: 14952
Member Admin
 

For all projects the user has planning rights to.


 
Posted : 03 Dec 2015 18H57
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

But the user is not a parameter of this function, how can I use the function PlannedWork->plan() into a shell script?


 
Posted : 16 Dec 2015 19H27
(@babynus)
Posts: 14952
Member Admin
 

how can I use the function PlannedWork->plan() into a shell script?

You cannot.
Thought a shelle script, you won't be connected to the application, so will have no rights to do any change in the database.
It is a security constraint.


 
Posted : 17 Dec 2015 13H13
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

So, I cannot refresh automatically all plannings. 👿

Could you consider this idea as an possible evolution?


 
Posted : 17 Dec 2015 13H27
(@babynus)
Posts: 14952
Member Admin
 

It is already planned (Ticket #1815) and will be integrated in several steps.
1) generate tag to indicate that a project requires re-planning
2) CRON the automatic planning


 
Posted : 17 Dec 2015 13H31
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Hi Babynus,

Do you have an estimated date or version for this evolution?

Thanks.


 
Posted : 11 Jan 2016 12H00
(@babynus)
Posts: 14952
Member Admin
 

Hi,

I cannot commit on a target date for this evolution.
It was first planned on V5.2, then V5.3 and recently moved to V5.4. Possibly it will move one on two versions back again. 😉
Sorry, but developement capacity is not very important, and priority is givzn to sponsored evolution.


 
Posted : 11 Jan 2016 12H52
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

No problem, I understand 🙂

It was just to have a more clear road map because this behavior is generated some "wrong planning" (i.e. some tasks was planned for last friday but the ressource didn't can work on this task, so without a manual recalculation, the planning was not updated to plan this task for today and move forward the other tasks initially planned for today.)


 
Posted : 11 Jan 2016 13H09