Maybe you could add new kind of reporting with:
- earn value (EV)
- planned value (PV)
- actuel cost (AC)

and maybe add new indicator on the project area with
- Schedule variance (SV)= EV - PV
- Schedule performance index (SPI)= EV/PV

what do you think?


 
Posted : 09 Apr 2013 18H36
(@babynus)
Posts: 14952
Member Admin
 

Request recorded as Ticket #1044.


 
Posted : 09 Apr 2013 21H53
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi all,

I support this request as well. Might be good, to have this EVA based on cost and on mandays / hours.

Klaus


 
Posted : 10 Apr 2013 11H50
DEDIEU
(@jcde)
Posts: 104
Active Member
 

I support this request as well.

this is a very good indicator.


 
Posted : 12 Apr 2013 0H13