Request:
Real work allocation - value in field "left" should be (if empty or as start value) same value as "assigned".
Activity planned value should show correct value incl. all assignments.
Case:
1. Activity, planned values are not correct, if "left" in real work allocation is empty.
2. In addition, planned values of all assigned resouces should be taken into this value as well - as a starting point / default.
If this is not correct added up, then planned value is wrong.
Solution proposal:
1. On every assignement to a activity, "planned" should be raised by addtional assigment.
2. If "left" on real work allocation is empty or default should be set to assigned work.
Hi,
Unless you discovered a bug in your configuration, the application is working the way you requested it on step 1 of Solution Proposal.
On every assignement, when updating Assigned work, left work is updated of the same value.
For instance :
- when creating new assignement, entering 5d for assigned work, left work is automatically updated to 5d
- updating an existing assignement, wiht 5d assigned work, 2d days left work, setting assigned to 6d days will update left to 3d
Then planned work is always calculated as : Planned = Real + Left.
Then, considering step 2, you discovered a bug in Real work allocation : when entering empty value to left work, it should be converted to zero value so that planned work should be calculated correctly.
Bug registered in track database as ticket #300.