A lot of my projects managers ask for an "Excel Export" in each report.
They would like to have in the excel file the same datas than the ones they see in the report (columns et lines).
They don't need any format (colors, etc..), but every number value must be in the good format (exemple : "1,25" instead of "1.25" for a days number)
Hi,
We have already estimated the work to export all reports to Excel.
The average cost to export a report file is estimated to 1 work day.
Each report file exports several reports (same report for different time frames).
ProjeQtOr includes 96 reports, generated with 63 report files.
12 of them cannot be exported to Excel (only chart for instance).
So we'll have to work 51 days on this subject.
Sure we won't spend this time without it beiong sponsored....
If you wish to sponsor it, please contact us.
Possibly we have another client that could share the cost.
I thought that a same code could be used on several reports. If not, i understand.
It's not so easy otherwise it would be done since long.
Each report file must be updated for Excel export... and it's not so easy.