Again Hi,
in fact we're using Projeqtor everyday more, i had several thoughts about improving the great tool.
so please excuse if i post to much.
we bought the screen customization plug-in and it works fine. but for our use we had some tricky needings. in tickets there is the "module" "ticket - work" and also in activities there is "activity - progress". for reporting some work and not changing the view to allocated work, we think the button "dispatch" in the ticket work module is a great opportunity. for planing projects the activity progress is essential (planning in progerss is a "must have" field). i thought if we can add such "modules" via the plugin to some forms it would be great. but by adding an extra field the possibility for using some already existing fields is not given. neither i am able to choose "objects" nor to pick some existing modules/fields.
is there a possibility to add this feature in the plugin?
do you understand my thinkings?
Sorry, I don't understand the request
Could you explain with an example what you expect ?
in my example there are 2 element/modules. activity progress and ticket-work. both are implemented in there needed masks as "objects".
if i try to configure the activity mask - i am not able to put in the existing object (Workelement). but i think the feature of marking allocated work in the activity mask would be great.
in common, the scree customization plugin can not add existing tables or field (maybe due to inconsistency problem that may occure) but combining such good elements from different masks could make a "master mask" which fits all our needs.
was this is little bit easier to understand?
if i try to configure the activity mask - i am not able to put in the existing object (Workelement). but i think the feature of marking allocated work in the activity mask would be great.
No, this won't work.
External objects (workelement, planninglement) cannot be simply added to an objet to have all work.
Sreen customization does not go so far...
To set an object as planable, other devs have to be integrated.
Activity is planable : it integrates PlanningElement
Ticket is workable : it integrates WorkElement
But Planable and Workable are not compatible : we cannot have object that integrates WorkElement AND PlanningElement.
thank you for your feedback